Jetty Modifications & Dredging Project.
Aden lies at the west end of the Gulf of Aden, on the direct shipping route
between Europe and Arabian Gulf. The Aden Refinery Company oil harbour is at the
Little Aden penninsula which is on the west side of Tawahi Bay.
Basically, Aden Refinery company oil harbour consists of four tankers
berths, two being single T-headed jetties, and the remaining two being sited on
either
side of a finger jetty. Tanker berths 1 & 2 each consist of a jetty head with
combined road and pipeway approach. Nine isolated mooring dolphins for these two
berths are provided
to take the ships ropes. Tanker berths 3 & 4 consist of a jetty head with
berthing faces on
each side and a combined road and pipeway approach. Four mooring dolphins are
provided, two inshore of the jetty head in the approach and two offshore of the
jetty head
and connected to it by a light footway. The oil harbour was constructed during
the period
of 1952 to 1954.
Aden Refinery Company essentially operates for various oil companies who bring
their own crude and collect the equivalent petroleum products on payment of a
processing fee. Due to the low availability of tankers of size below 55,000 SDWT
in market, the various oil companies have expressed difficulties in chartering
these sizes of tankers and have been requesting ARC for facilities to receive
bigger tankers. In view of this, ARC have decided to develop a deep water oil
terminal for receiving bigger tankers
up to 110,000 SDWT.
1)SCOPE OF THE PROJECT WORKS.
The project works include the following principal elements to be carried out at
the oil harbour .
a)
The rehabilitation of existing oil berths No.1, 2, 3 and upgrading berth No.4;
which includes:-
1)
Demolishing the existing concrete jetty head decks.
2)
Repairing the conrete on the approach roads, walkways, and mooring dolphins.
3) Repairing the steelwork on the jetty heads and approach arms.
4) Reconstructing the concrete jetty heads including new jetty buildings.
5) Constructing new independent central fenders at Berth 1 & 2.
b)
The construction of new berthing dolphins at Berth 4.
c)
Dredging of the harbour area.
d)
Dredging the existing approah channel deeper and wider and extending
this beyond the present Fairway buoy to the -15m. contour.
e) Building new Navigational approah channel beacons, re-establishing
existing and installing new channel markers.
f)
Mechanical And Electrical.
The existing loading facilities which were installed in 1954, consist of
flow jib cranes mounted on an elevated structure on each of four jetties.
Each crane is capable of handling a single flexible 8" dia. hose between the
jetty manifold and the tanker manifold.
At present Jetties Nos.1 & 2 have 23 jetty manifold connections whilst jetties
Nos. 3 & 4 have 28 connections.
The existing loading facilities were replaced with new all metal loading arms
which are manifolded together, for compatible products, thus reducing the number
of loading arms required per jetty.
Other equipment which are replaced includes the jetty manifolds and valves,
slops pumps, motors,floodlighting, switchgear. cabling and instrumentation in
order to accommodate crude carriers of up to 110,000 SDWT Berth No.4. was
upgraded. Fire fighting facilities at the jetty areas were also upgraded.
2) Additional Rehabilitation Works.
The rehabilitation of the following small Jetties was added to the scope of
J.M.D. Project Contract:-
(1)
Marine Stores Jetty.
(2) Tug Boat Jetty.
(3) Launch Jetty.
(4) Fire Pump House and Water Intake.
3)Additional New Construction & Dredging Works.
The construction of the following new Jetties and dredging works also
was added to the scope of J.M.D. Project Contract:-
(1) New
Asphalt Jetty.
(2) New Asphalt Jetty extension.
(3) New LPG Jetty.
(4) Dredging Works at the Asphalt and LPG Jetties upto-11 C.D.
JETTY MODIFICATIONS AND DREDGING PROJECT
1)
Contract signed with CCC on December 9, 1985.
2) Order
to commence the work given on July 9, 1986.
3)
Dredging activity started on September 24, 1986.
5) " "
completed on July, 1987.
6)
Actual rehabilitation works on Berth 1 started on October, 1986.
7) Berth
1 commission on July 16, 1988.
8) Works
on Berth 2 started on November 2, 1987.
9) Berth
2 commissioned on August 26, 1988.
10)
Rehabilitation works on Berths 3 & 4 started on September 11, 1988.
11)
Berth 3 & 4 commission on June 18, 1989.
12)
Marine Stores Jetty commissioned on July 9th , 1989.
13) Tug
Boat commissioned on July 9th, 1989.
14) Fire
P/H & water intake commissioned on July 11th, 1989.
15) The
construction of the new Asphalt Jetty Extension was started on 6th oct, 1990 and
work was completed on 2nd July, 1991.
16) The construction of the new LPG Jetty started on 9th Sept, and the work was
completed on Dec. 31st 1992.
17) The
Dredging works at the Asphalt and LPG Jetties started on 20 June 93 and all
Dredging Works completed on 29th July, 1993.